Petra Flašker and the Notion of Doubts in the Context of Preliminary Investigations of Both New and Existing Measures · Case T-392/20 Flašker v Commission · Annotation by Marianne Clayton, Gaétan Roelants du Vivier and Matthieu Jamart journal article

Annotation on the Judgment of the General Court (Fourth Chamber) of 27 April 2022 in Case T-392/20 Flašker v Commission

Marianne Clayton, Gaétan Roelants du Vivier, Matthieu Jamart

European State Aid Law Quarterly, Volume 22 (2023), Issue 1, Page 89 - 94

The judgment of the General Court in Case T-392/20 Flašker v Commission addresses the procedural concept of serious difficulties and the scope of the Commission’s obligation, when investigating complaints, to carry out a thorough examination beyond the mere information provided by the complainants and the national authorities which is also applicable in the context of existing aid. In particular, the General Court reaffirmed the Commission’s responsibility to conduct a proper investigation when faced with serious allegations and insisted that the Commission cannot rely on the fact that the complaint may not be sufficiently substantiated as an argument for dismissing it. More novel, the General Court noted that the Commission had disregarded the existing procedural rules by adopting a decision finding that, assuming that a measure constitutes aid, it amounts to existing aid, but unfortunately did not draw any further conclusions.


‘Prior in Tempore, Potior in Jure’ Does Not Exclude State Aid to Users of Infrastructure · Case T-108/16 Naviera Armas · Annotation  Marianne Clayton, Egill Olafsson and Maria Segura journal article

Annotation on the Judgment of the General Court of 15 March 2018 in Case T-108/16 Naviera Armas SA

Marianne Clayton, Egill Olafsson, Maria Segura

European State Aid Law Quarterly, Volume 17 (2018), Issue 2, Page 282 - 289

On 15 March 2018, the General Court annulled a Commission Decision which considered that the Spanish authorities had not granted state aid in favour of Fred Olsen through some measures relating to the port of Puerto de Las Nieves in the Canary Islands. A competitor, who had complained to the Commission about the said measures, applied for annulment of the Commission’s Decision on the grounds that the Commission should have opened the formal investigation procedure resulting from the fact that it had encountered serious difficulties. Even though the Decision had been appealed on the grounds of procedure, by its nature, the Court had to go into the substance of the case. The line between procedure and substance can be a fine one. Keywords: Opening Formal Investigation; Serious Difficulties; Use of State-Owned Infrastructure.

  • «